About the Book |
|
xiii | |
About the Author |
|
xv | |
1 Introduction |
|
1 | (4) |
|
Ten Things You Need to Know |
|
|
1 | (1) |
|
|
2 | (3) |
2 The Contract |
|
5 | (14) |
|
|
5 | (1) |
|
|
5 | (1) |
|
|
5 | (1) |
|
Stimulus to Good Management |
|
|
6 | (1) |
|
|
6 | (1) |
|
|
6 | (1) |
|
|
7 | (2) |
|
|
7 | (1) |
|
Flow Charts and Guidance Notes |
|
|
8 | (1) |
|
|
9 | (1) |
|
|
9 | (1) |
|
|
9 | (5) |
|
Option A - Priced Contract with Activity Schedule |
|
|
10 | (1) |
|
Option B - Priced Contract with Bill of Quantities |
|
|
11 | (1) |
|
Option C - Target Contract with Activity Schedule |
|
|
11 | (1) |
|
Option D - Target Contract with Bill of Quantities |
|
|
12 | (1) |
|
Option E - Cost Reimbursable Contract |
|
|
12 | (1) |
|
Option F - Management Contract |
|
|
13 | (1) |
|
|
13 | (1) |
|
|
14 | (1) |
|
|
14 | (1) |
|
|
14 | (1) |
|
|
15 | (1) |
|
|
15 | (1) |
|
|
16 | (1) |
|
The Schedule of Cost Components |
|
|
16 | (1) |
|
The Shorter Schedule of Cost Components |
|
|
16 | (1) |
|
Formation of the Contract |
|
|
16 | (1) |
|
|
16 | (1) |
|
|
17 | (1) |
|
Necessary Contract Documents |
|
|
17 | (1) |
|
Frequently Asked Questions |
|
|
17 | (2) |
3 General |
|
19 | (52) |
|
|
19 | (1) |
|
|
19 | (15) |
|
|
20 | (2) |
|
|
22 | (5) |
|
|
27 | (5) |
|
|
32 | (1) |
|
|
32 | (1) |
|
|
33 | (1) |
|
Identified and Defined Terms |
|
|
34 | (23) |
|
|
35 | (1) |
|
|
36 | (2) |
|
|
38 | (1) |
|
|
38 | (1) |
|
|
39 | (1) |
|
|
39 | (1) |
|
|
40 | (1) |
|
|
40 | (1) |
|
|
41 | (1) |
|
|
42 | (1) |
|
|
42 | (1) |
|
|
42 | (1) |
|
|
43 | (1) |
|
|
44 | (1) |
|
|
44 | (1) |
|
|
45 | (1) |
|
|
45 | (1) |
|
|
46 | (1) |
|
|
46 | (3) |
|
20 The Activity Schedule (Main Options A and C Only) |
|
|
49 | (3) |
|
Who Prepares the List of Activities? |
|
|
49 | (1) |
|
What Should be Included in the Schedule? |
|
|
50 | (1) |
|
Relationship to the Accepted Programme |
|
|
50 | (1) |
|
Changes to the Activity Schedule |
|
|
50 | (1) |
|
|
51 | (1) |
|
|
51 | (1) |
|
Errors in the Activity Schedule |
|
|
51 | (1) |
|
21 The Bill of Quantities (Main Options B and D Only) |
|
|
52 | (2) |
|
Changes to the Bill of Quantities |
|
|
53 | (1) |
|
|
53 | (1) |
|
|
53 | (1) |
|
Errors in the Bill of Quantities |
|
|
54 | (1) |
|
|
54 | (1) |
|
|
54 | (1) |
|
|
54 | (1) |
|
|
55 | (1) |
|
|
55 | (1) |
|
27 Price for Work Done to Date (Option A) |
|
|
56 | (1) |
|
28 Price for Work Done to Date (Option B) |
|
|
56 | (1) |
|
29 Price for Work Done to Date (Options C to F) |
|
|
57 | (1) |
|
30 Prices (Main Options A and C) |
|
|
57 | (1) |
|
31 Prices (Main Options B and D) |
|
|
57 | (1) |
|
32 Prices (Main Options E and F) |
|
|
57 | (1) |
|
33 The Total of the Prices (Option D) |
|
|
57 | (1) |
|
Interpretation and the Law |
|
|
57 | (1) |
|
|
58 | (2) |
|
|
59 | (1) |
|
The Project Manager and the Supervisor |
|
|
60 | (1) |
|
Adding to the Working Areas |
|
|
61 | (1) |
|
|
61 | (2) |
|
Ambiguities and Inconsistencies |
|
|
63 | (1) |
|
Illegalities and Impossibilities |
|
|
64 | (1) |
|
|
64 | (1) |
|
Frequently Asked Questions |
|
|
65 | (6) |
4 The Contractor's Main Responsibilities |
|
71 | (18) |
|
|
71 | (6) |
|
|
77 | (1) |
|
|
78 | (1) |
|
Acceptance of the Contractor's Design |
|
|
78 | (1) |
|
Using the Contractor's Design |
|
|
79 | (1) |
|
|
79 | (1) |
|
|
80 | (1) |
|
Working With the Employer and Others |
|
|
81 | (1) |
|
|
82 | (2) |
|
|
84 | (1) |
|
Frequently Asked Questions |
|
|
85 | (4) |
5 Time |
|
89 | (16) |
|
|
89 | (1) |
|
Starting, Completion and Key Dates |
|
|
89 | (2) |
|
Commencement and Completion |
|
|
89 | (1) |
|
|
90 | (1) |
|
|
91 | (1) |
|
|
91 | (5) |
|
|
92 | (1) |
|
Information on the Programme |
|
|
92 | (3) |
|
Acceptance of the Programme |
|
|
95 | (1) |
|
Rejection of the Programme |
|
|
95 | (1) |
|
|
96 | (2) |
|
Access to and Use of the Site |
|
|
98 | (1) |
|
Instructions to Stop or Not to Start the Work |
|
|
98 | (1) |
|
|
98 | (1) |
|
|
99 | (1) |
|
Frequently Asked Questions |
|
|
100 | (5) |
6 Testing and Defects |
|
105 | (10) |
|
|
105 | (1) |
|
|
106 | (1) |
|
Tests and Inspections Before Delivery |
|
|
107 | (1) |
|
Searching For and Notifying Defects |
|
|
107 | (1) |
|
|
107 | (1) |
|
|
108 | (1) |
|
|
108 | (1) |
|
|
108 | (1) |
|
|
108 | (1) |
|
|
109 | (1) |
|
|
109 | (1) |
|
|
110 | (1) |
|
Frequently Asked Questions |
|
|
111 | (4) |
7 Payment |
|
115 | (24) |
|
|
115 | (1) |
|
|
115 | (13) |
|
|
116 | (1) |
|
|
117 | (1) |
|
|
117 | (3) |
|
Amounts Due to Subcontractors |
|
|
118 | (1) |
|
The Cost of Components in the Schedule of Cost Components |
|
|
119 | (1) |
|
|
119 | (1) |
|
|
120 | (1) |
|
|
120 | (2) |
|
Amounts Due to Subcontractors |
|
|
121 | (1) |
|
The Cost of Components in the Schedule of Cost Components |
|
|
121 | (1) |
|
|
121 | (1) |
|
|
122 | (1) |
|
|
122 | (3) |
|
Amounts Due to Subcontractors |
|
|
123 | (1) |
|
The Cost of Components in the Schedule of Cost Components |
|
|
124 | (1) |
|
|
124 | (1) |
|
|
125 | (1) |
|
|
125 | (3) |
|
Amounts Due to Subcontractors |
|
|
126 | (1) |
|
The Prices for the Work Done by the Contractor |
|
|
127 | (1) |
|
|
127 | (1) |
|
|
127 | (1) |
|
Unfixed Materials on Site |
|
|
128 | (1) |
|
|
128 | (1) |
|
|
128 | (1) |
|
|
128 | (1) |
|
|
128 | (1) |
|
|
128 | (1) |
|
|
128 | (4) |
|
|
129 | (1) |
|
The Secondary Legislation |
|
|
129 | (1) |
|
|
129 | (1) |
|
A 'Construction Contract' |
|
|
129 | (1) |
|
|
130 | (1) |
|
|
130 | (1) |
|
|
131 | (1) |
|
|
132 | (1) |
|
|
132 | (1) |
|
|
133 | (1) |
|
|
134 | (1) |
|
|
135 | (1) |
|
Frequently Asked Questions |
|
|
135 | (4) |
8 Compensation Events |
|
139 | (30) |
|
|
139 | (1) |
|
|
140 | (1) |
|
Core Clause Compensation Events |
|
|
140 | (9) |
|
|
146 | (1) |
|
|
146 | (1) |
|
|
146 | (3) |
|
Bill of Quantity Compensation Events |
|
|
149 | (1) |
|
Secondary Option Compensation Events |
|
|
150 | (1) |
|
Clause X2.1 - Changes in the Law |
|
|
150 | (1) |
|
Clause X12.3(6) and (7) - Changes in Partnering Information |
|
|
151 | (1) |
|
Clause X14.2 - Delay in Making Advanced Payment |
|
|
151 | (1) |
|
Clause X15.2 - Correction of a Defect |
|
|
151 | (1) |
|
Clause Y2.4 - Suspension Under the Housing Grants, Construction and Regeneration Act 1996 |
|
|
151 | (1) |
|
Compensation Event Procedure |
|
|
151 | (10) |
|
Notifying Compensation Events |
|
|
151 | (3) |
|
Quotations for Compensation Events |
|
|
154 | (2) |
|
Assessing Compensation Events |
|
|
156 | (3) |
|
Effect of the Event on Defined Cost |
|
|
157 | (1) |
|
Effect of the Event on Planned Completion |
|
|
158 | (1) |
|
Failure to Give Early Warning |
|
|
159 | (1) |
|
The Project Manager's Assessment |
|
|
159 | (2) |
|
|
161 | (1) |
|
Implementing Compensation Events |
|
|
161 | (1) |
|
|
161 | (2) |
|
|
163 | (1) |
|
|
164 | (1) |
|
Frequently Asked Questions |
|
|
164 | (5) |
9 Title |
|
169 | (4) |
|
|
169 | (1) |
|
The Employer's Title to Plant and Materials |
|
|
169 | (1) |
|
Marking Equipment, Plant and Materials Outside the Working Areas |
|
|
170 | (1) |
|
|
171 | (1) |
|
Objects and Materials within the Site |
|
|
171 | (1) |
|
Frequently Asked Questions |
|
|
171 | (2) |
10 Risks and Insurance |
|
173 | (6) |
|
|
173 | (1) |
|
|
173 | (1) |
|
|
174 | (1) |
|
|
175 | (1) |
|
|
175 | (1) |
|
|
175 | (1) |
|
|
176 | (1) |
|
If the Contractor Does Not Insure |
|
|
176 | (1) |
|
Insurance by the Employer |
|
|
177 | (1) |
|
Frequently Asked Questions |
|
|
177 | (2) |
11 Termination |
|
179 | (6) |
|
|
179 | (1) |
|
|
179 | (1) |
|
|
180 | (1) |
|
Procedures on Termination |
|
|
181 | (1) |
|
|
181 | (2) |
|
Frequently Asked Questions |
|
|
183 | (2) |
12 Dispute Resolution (W1 and W2 Adjudication) |
|
185 | (18) |
|
|
185 | (1) |
|
|
185 | (7) |
|
|
185 | (1) |
|
|
186 | (2) |
|
|
188 | (3) |
|
|
191 | (1) |
|
|
192 | (8) |
|
|
192 | (1) |
|
|
193 | (3) |
|
|
196 | (3) |
|
|
199 | (1) |
|
Frequently Asked Questions |
|
|
200 | (3) |
13 X and Y Clauses |
|
203 | (12) |
|
|
203 | (1) |
|
|
203 | (6) |
|
X1 - Price Adjustment for Inflation |
|
|
203 | (1) |
|
|
204 | (1) |
|
|
204 | (1) |
|
X4 - Parent Company Guarantees |
|
|
205 | (1) |
|
X5 - Sectional Completion |
|
|
205 | (1) |
|
X6 - Bonus for Early Completion |
|
|
205 | (1) |
|
|
206 | (1) |
|
|
206 | (1) |
|
|
207 | (1) |
|
X14 - Advanced Payment to the Contractor |
|
|
207 | (1) |
|
X15 - Limitation of Contractor's Liability for his Design to Reasonable Skill and Care |
|
|
207 | (1) |
|
X17 - Low Performance Damages |
|
|
208 | (1) |
|
X18 - Limitation of Liability |
|
|
208 | (1) |
|
X20 - Key Performance Indicators |
|
|
209 | (1) |
|
|
209 | (4) |
|
Y(UK)1 - Project Bank Account |
|
|
209 | (3) |
|
|
209 | (1) |
|
|
210 | (1) |
|
|
210 | (1) |
|
|
210 | (1) |
|
|
211 | (1) |
|
|
211 | (1) |
|
|
211 | (1) |
|
|
211 | (1) |
|
Y (UK)2 - Housing Grants, Construction and Regeneration Act 1996 |
|
|
212 | (1) |
|
|
212 | (1) |
|
|
212 | (1) |
|
|
212 | (1) |
|
Notice of Intention to Pay Less |
|
|
212 | (1) |
|
Suspension of Performance |
|
|
212 | (1) |
|
Y(UK)3 - Contracts (Rights of Third Parties) Act 1999 |
|
|
213 | (6) |
|
|
213 | (1) |
|
Frequently Asked Questions |
|
|
213 | (2) |
14 Z Clauses |
|
215 | (4) |
|
|
215 | (1) |
|
Additional Conditions of Contract |
|
|
215 | (1) |
|
Frequently Asked Questions |
|
|
216 | (3) |
15 Schedules of Cost Components |
|
219 | (10) |
|
|
219 | (1) |
|
Schedule of Cost Components |
|
|
219 | (4) |
|
|
220 | (1) |
|
|
220 | (1) |
|
|
220 | (1) |
|
|
221 | (1) |
|
|
222 | (1) |
|
Manufacture and Fabrication |
|
|
222 | (1) |
|
|
222 | (1) |
|
|
222 | (1) |
|
Shorter Schedule of Cost Components |
|
|
223 | (3) |
|
|
223 | (1) |
|
|
223 | (1) |
|
|
224 | (1) |
|
|
225 | (1) |
|
|
225 | (1) |
|
Manufacture and Fabrication |
|
|
225 | (1) |
|
|
225 | (1) |
|
|
226 | (1) |
|
Frequently Asked Questions |
|
|
226 | (3) |
Index |
|
229 | |