Preface |
|
xi | |
|
An Introduction to Design-Build |
|
|
1 | (16) |
|
The Search for a Better System |
|
|
2 | (1) |
|
How the Construction Industry Is Perceived |
|
|
2 | (2) |
|
The Case for Design-Build |
|
|
4 | (1) |
|
The master builder approach |
|
|
4 | (1) |
|
|
5 | (1) |
|
Build-operate-transfer---carrying design-build further |
|
|
5 | (1) |
|
HUD and Government's Entrance Into Design-Build |
|
|
5 | (1) |
|
The Design-Build Advantage |
|
|
6 | (2) |
|
Public Sector Interest in Design-Build |
|
|
8 | (1) |
|
The Challenges of Design-Build |
|
|
9 | (2) |
|
|
9 | (1) |
|
|
10 | (1) |
|
Liability, bonding, licensing issues |
|
|
10 | (1) |
|
The Life Cycle of a Design-Build Process |
|
|
11 | (3) |
|
|
11 | (1) |
|
|
11 | (1) |
|
|
12 | (1) |
|
Project planning---formulation of the performance specifications |
|
|
13 | (1) |
|
Contract award and construction administration |
|
|
13 | (1) |
|
Closeout and commissioning |
|
|
14 | (1) |
|
|
14 | (1) |
|
|
15 | (2) |
|
Traveling the Path to Design-Build |
|
|
17 | (36) |
|
|
18 | (1) |
|
Dispute Resolution Measures |
|
|
19 | (1) |
|
The Cost-Plus-Guaranteed Maximum Price Contract |
|
|
19 | (1) |
|
|
20 | (1) |
|
|
20 | (1) |
|
|
20 | (1) |
|
|
21 | (1) |
|
|
21 | (1) |
|
The Design-Build Process---Searching for the Holy Grail |
|
|
22 | (3) |
|
Negotiated design-build projects |
|
|
22 | (1) |
|
Competitively bid design-build work |
|
|
23 | (2) |
|
Design-build has its advantages and its disadvantages |
|
|
25 | (1) |
|
The Bridging Approach to Design-Build |
|
|
25 | (1) |
|
How Effective Is Design-Build? |
|
|
26 | (4) |
|
|
30 | (7) |
|
The owner's quality responsibilities |
|
|
33 | (2) |
|
How should quality management issues be addressed by owners |
|
|
35 | (2) |
|
The Austin Company of Cleveland, Ohio---A Case Study in Design-Build Evolution |
|
|
37 | (10) |
|
The Austin Company in 2005 |
|
|
46 | (1) |
|
A Midsize Contractor's View of Design-Build |
|
|
47 | (6) |
|
A closer look at Forrester's QDP approach |
|
|
49 | (4) |
|
|
53 | (26) |
|
Different Approaches to Assembling a Design-Build Team |
|
|
53 | (1) |
|
|
53 | (1) |
|
|
54 | (1) |
|
The New Business Entity---Joint Venture, Teaming Agreement, Limited Liability Corporation, or S Corporation? |
|
|
54 | (8) |
|
|
54 | (1) |
|
|
55 | (6) |
|
The limited liability corporation |
|
|
61 | (1) |
|
|
61 | (1) |
|
|
62 | (1) |
|
|
62 | (1) |
|
Architect-or Contractor-Led Team? |
|
|
62 | (5) |
|
Contractor as team leader |
|
|
62 | (1) |
|
Contractor as prime contractor, architect as subcontractor |
|
|
63 | (1) |
|
|
64 | (2) |
|
Architect as prime contractor, builder as subcontractor |
|
|
66 | (1) |
|
Architect as participant in a JV or an LLC with a contractor on a project-specific basis |
|
|
67 | (1) |
|
The Collaborative Approach |
|
|
67 | (1) |
|
Other Essential Elements of the Design-Build Team |
|
|
67 | (4) |
|
The design-build safety program |
|
|
68 | (3) |
|
|
71 | (1) |
|
|
72 | (5) |
|
A Sample Teaming Agreement for Architect and Contractor |
|
|
77 | (2) |
|
The Design and Construction Industries |
|
|
79 | (20) |
|
The Industry According to the U.S. Department of Labor |
|
|
79 | (1) |
|
The Construction Industry |
|
|
80 | (12) |
|
Construction financial management association |
|
|
80 | (1) |
|
Strategic planning---the Hot Topic |
|
|
80 | (12) |
|
The Architect-Engineering Professions |
|
|
92 | (5) |
|
|
97 | (2) |
|
Developing a Design-Build Program |
|
|
99 | (10) |
|
Building on What You Have |
|
|
99 | (1) |
|
The niche market approach |
|
|
100 | (1) |
|
Sports and Recreational Facilities |
|
|
100 | (3) |
|
|
101 | (2) |
|
Security and Design-Build |
|
|
103 | (1) |
|
Green Buildings and Sustainable Construction |
|
|
104 | (1) |
|
Design-Build in the Process and Biotech Industries |
|
|
104 | (1) |
|
|
105 | (1) |
|
Business Development and Design-Build |
|
|
105 | (1) |
|
Building client relations |
|
|
105 | (1) |
|
Developing a Follow-Up Plan |
|
|
106 | (1) |
|
Producing Effective Presentations |
|
|
106 | (3) |
|
|
107 | (2) |
|
Design-Build in the Public Sector |
|
|
109 | (32) |
|
The Federal Government and Design-Build |
|
|
110 | (1) |
|
The States Use Design-Build |
|
|
110 | (2) |
|
What Other States Are Doing |
|
|
112 | (1) |
|
Quicker Delivery of Design-Build Projects |
|
|
113 | (1) |
|
|
113 | (1) |
|
Licensing Laws Affecting Design-Build |
|
|
114 | (1) |
|
Bidders point out some shortfalls in the process |
|
|
114 | (1) |
|
|
115 | (1) |
|
Private Sector Teams Learning from Public Sector Procedures |
|
|
115 | (2) |
|
The two-part RFP on the federal and state levels |
|
|
115 | (2) |
|
Requirements for Complying with the Prequalification Phase of a Design-Build RFP |
|
|
117 | (1) |
|
|
118 | (2) |
|
State of Maryland weighted evaluation approach |
|
|
118 | (1) |
|
Maryland adds flexibility to the evaluation process |
|
|
119 | (1) |
|
ADOT's Short Bidder's Compensation Provision |
|
|
120 | (1) |
|
State of California as Innovator |
|
|
120 | (4) |
|
Design-build--stipulated sum contract award |
|
|
122 | (2) |
|
|
124 | (2) |
|
Appendix 6.1: Minnesota Department of Transportation Evaluation Procedure |
|
|
126 | (15) |
|
The Construction Manager Approach to Design-Build |
|
|
141 | (56) |
|
|
142 | (1) |
|
|
142 | (1) |
|
The Selection of a Construction Management Firm by Prequalifying |
|
|
143 | (1) |
|
Risk Management and the Role of the CM |
|
|
144 | (1) |
|
The need for a contingency account |
|
|
144 | (1) |
|
The Role of the Construction Manager during Design |
|
|
145 | (4) |
|
The responsibilities of the CM during the construction phase |
|
|
148 | (1) |
|
The CM's postconstruction activities |
|
|
149 | (1) |
|
Other Construction Management Contracts |
|
|
149 | (5) |
|
|
150 | (4) |
|
|
154 | (2) |
|
Construction Management Fees |
|
|
156 | (1) |
|
|
156 | (1) |
|
An Owner Exercises a CM Option |
|
|
157 | (1) |
|
The United States Postal Service---A Long Time CM/Design-Build Advocate |
|
|
158 | (2) |
|
|
159 | (1) |
|
The Individual Purchasing Plan |
|
|
160 | (1) |
|
GMP Contracts Add to the CM Responsibility |
|
|
161 | (1) |
|
The CM's Participation in Evaluating Design-Build Proposals |
|
|
162 | (4) |
|
Can there truly be an objective evaluation system? |
|
|
162 | (4) |
|
Construction Management Contracts Used by the USPS |
|
|
166 | (1) |
|
|
166 | (1) |
|
Design-build competitively bid GMP type contract |
|
|
166 | (1) |
|
Design-build two-phase proposal |
|
|
166 | (1) |
|
The Design-Builder Prequalification Process |
|
|
167 | (1) |
|
Appendix 7.1: CMAA Document A-1 Owner & Construction Manager Contract |
|
|
168 | (12) |
|
Appendix 7.2: Design-Build Qualification Statement Package |
|
|
180 | (17) |
|
Design-Build and Sustainability |
|
|
197 | (30) |
|
The Impact of Construction on the Environment |
|
|
198 | (1) |
|
What do we mean by sustainability? |
|
|
198 | (1) |
|
|
199 | (1) |
|
LEED Is Not Sustainability |
|
|
199 | (7) |
|
Government takes the LEED |
|
|
206 | (1) |
|
Green Buildings in the Private Sector |
|
|
206 | (2) |
|
|
207 | (1) |
|
Are Green Buildings More Expensive than Conventional Construction? |
|
|
208 | (6) |
|
|
213 | (1) |
|
|
214 | (1) |
|
The Sustainable Approach to Design |
|
|
214 | (1) |
|
The Sustainable Approach to Construction |
|
|
215 | (1) |
|
The Holistic Approach---Again |
|
|
216 | (1) |
|
NREL and Oberlin College's Pilot Program |
|
|
217 | (3) |
|
Greening of Existing Buildings |
|
|
220 | (7) |
|
Johnson Diversey upgrade of an existing building |
|
|
220 | (7) |
|
Interoperability and Building Information Modeling |
|
|
227 | (28) |
|
Looking at the Past Three Decades |
|
|
227 | (1) |
|
Contractors and Architects and the Early Electronic World |
|
|
228 | (2) |
|
The transfer from diskette to Internet provider |
|
|
229 | (1) |
|
Contractors slow to embrace |
|
|
229 | (1) |
|
|
230 | (1) |
|
Interoperability---What Is It and Why Is It So Important? |
|
|
231 | (1) |
|
|
231 | (6) |
|
Why are contractors deficient in information management? |
|
|
237 | (1) |
|
The Federal Government Push for Interoperability and Building Information Modeling |
|
|
237 | (1) |
|
Interoperability and BIM issues |
|
|
238 | (1) |
|
The Industry Movement Toward Interoperability |
|
|
238 | (1) |
|
The Current State of Affairs |
|
|
239 | (1) |
|
The Steel Industry Becomes a Leader |
|
|
240 | (3) |
|
Interoperability and BIM as envisioned by the steel industry |
|
|
241 | (2) |
|
Case Study---The Lansing Community College Project, Lansing, Michigan |
|
|
243 | (1) |
|
The Denver Art Museum Project |
|
|
244 | (2) |
|
|
246 | (1) |
|
What Is Building Information Modeling All About? |
|
|
246 | (2) |
|
|
248 | (3) |
|
BIM---Its Promises and Its Problems |
|
|
251 | (4) |
|
BIM can provide higher quality |
|
|
251 | (1) |
|
|
252 | (1) |
|
|
253 | (2) |
|
Bond and Insurance Considerations and Issues |
|
|
255 | (30) |
|
|
255 | (1) |
|
|
256 | (1) |
|
The top five factors for contractor failure |
|
|
256 | (1) |
|
Another study about contractor failures |
|
|
257 | (1) |
|
Warning Signs That a Contractor Is In Trouble |
|
|
257 | (1) |
|
|
258 | (1) |
|
A subtle but significant change in liability |
|
|
258 | (1) |
|
|
259 | (1) |
|
Bonds and Letters of Credit |
|
|
259 | (1) |
|
The terminology of bonding |
|
|
260 | (1) |
|
|
260 | (1) |
|
|
261 | (1) |
|
|
261 | (1) |
|
Suggestions for the Newly Created Design-Build Teams---the Three Cs |
|
|
262 | (1) |
|
|
262 | (1) |
|
|
262 | (1) |
|
|
262 | (1) |
|
Traveling In Newly Charted Waters |
|
|
263 | (1) |
|
|
264 | (2) |
|
Bonds and the contractor-led design-build team |
|
|
264 | (1) |
|
Bonds and the A/E led team |
|
|
265 | (1) |
|
Bond Provisions in the Contract |
|
|
266 | (1) |
|
Insuring Design-Build Risks |
|
|
267 | (5) |
|
General liability insurance |
|
|
268 | (1) |
|
Commercial general liability |
|
|
268 | (4) |
|
What Effect Does a Hold Harmless Clause Have? |
|
|
272 | (1) |
|
Risks associated with design |
|
|
272 | (1) |
|
The Standard of Care Standard |
|
|
273 | (3) |
|
Another twist to the liability issue |
|
|
273 | (1) |
|
Risk management through E&O insurance |
|
|
274 | (2) |
|
The Necessity for Builder's Risk insurance |
|
|
276 | (1) |
|
The Need for Waivers of Subrogation |
|
|
277 | (1) |
|
Workers Compensation Insurance |
|
|
277 | (1) |
|
How premiums are established |
|
|
277 | (1) |
|
Controlled Insurance Programs |
|
|
278 | (7) |
|
|
282 | (3) |
|
The Legal Aspects of Design-Build |
|
|
285 | (16) |
|
|
286 | (1) |
|
|
287 | (1) |
|
Liability under design-build |
|
|
287 | (1) |
|
|
288 | (1) |
|
|
288 | (1) |
|
|
289 | (1) |
|
Contractor's licensing laws |
|
|
290 | (1) |
|
How the Law Looks at Design-Build |
|
|
290 | (1) |
|
Failure to Control the Design |
|
|
291 | (1) |
|
Other Legal Issues That Confront an Architect-Led Design-Build Team |
|
|
291 | (2) |
|
Liability for design errors: statutes of limitations limits |
|
|
292 | (1) |
|
|
292 | (1) |
|
Other ownership and use considerations |
|
|
293 | (1) |
|
|
293 | (1) |
|
The Implied Terms in a Design-Build Project |
|
|
294 | (1) |
|
Compliance with code responsibility |
|
|
295 | (1) |
|
The Uniform Commercial Code |
|
|
295 | (1) |
|
Americans with Disabilities Act |
|
|
296 | (1) |
|
Green Buildings---Avoiding Some Not-Too-Obvious Pitfalls |
|
|
297 | (1) |
|
Paybacks on Capital Costs That May or May Not Occur |
|
|
298 | (1) |
|
The Sick Building Concern |
|
|
298 | (1) |
|
The Legal Implication of Electronic Records |
|
|
298 | (1) |
|
|
299 | (2) |
|
|
301 | (52) |
|
Exhibits---When More Clarity Is Required |
|
|
302 | (1) |
|
|
302 | (1) |
|
Reimbursable design-build personnel costs |
|
|
303 | (1) |
|
Costs Not to Be Reimbursed |
|
|
303 | (1) |
|
Dealing with Allowances and Alternates |
|
|
304 | (1) |
|
|
305 | (1) |
|
|
306 | (1) |
|
Everything Is Included in the Article |
|
|
306 | (1) |
|
|
307 | (3) |
|
|
307 | (3) |
|
|
310 | (1) |
|
An Owner Viewpoint about Design-Build Contract Provisions |
|
|
310 | (1) |
|
|
311 | (1) |
|
Understanding Dispute and Claims Resolution Options |
|
|
312 | (1) |
|
The Schedule of Values Line Item Issue |
|
|
312 | (1) |
|
The Importance of Substantial Completion |
|
|
313 | (1) |
|
The Standard Form Contracts |
|
|
314 | (8) |
|
The American Institute of Architects contracts |
|
|
314 | (2) |
|
Construction Management contracts |
|
|
316 | (1) |
|
The Associated General Contractors of America contracts |
|
|
316 | (4) |
|
The Engineers Joint Contract Documents Committee |
|
|
320 | (2) |
|
Appendix 12.1: Teaming Agreement Prepared by the Associated General Contractors of America (AGC) |
|
|
322 | (4) |
|
Appendix 12.2: AGC Document 410---Standard Form of Design-Build Agreement between Owner and Design-Builder |
|
|
326 | (27) |
|
Where Do We Go from Here? |
|
|
353 | (12) |
|
Interoperability Coupled with Outsourcing |
|
|
353 | (1) |
|
|
354 | (4) |
|
The Supply Chain Productivity Issue |
|
|
358 | (1) |
|
Well, Help Is on the Way in the Form of Global Positioning Satellites and Radio Frequency Identification Devices |
|
|
359 | (2) |
|
Global positioning satellites |
|
|
359 | (1) |
|
Radio frequency Identification devices |
|
|
359 | (2) |
|
RFIDs Make Concrete Pours More Effective |
|
|
361 | (1) |
|
Where Are the Advances in Construction Components and Materials? |
|
|
361 | (1) |
|
Is the A/E/C Industry Becoming Just Another IT Business? |
|
|
362 | (3) |
Index |
|
365 | |