|
|
xv | |
|
|
xxi | |
About the authors |
|
xxiii | |
|
|
xxv | |
Acknowledgements |
|
xxvii | |
|
List of acronyms and abbreviations |
|
|
xxix | |
|
Chapter 1 Introduction To Floating Production |
|
|
1 | (19) |
|
|
|
A Floating production as a legal topic |
|
|
1 | (1) |
|
|
2 | (4) |
|
|
3 | (1) |
|
|
4 | (1) |
|
|
5 | (1) |
|
|
5 | (1) |
|
|
5 | (1) |
|
(vi) Is an FLNG a type of FPSO? |
|
|
6 | (1) |
|
(vii) Is an FLSO an FLNG or an FPSO? |
|
|
6 | (1) |
|
C What is an FPSO charter? |
|
|
6 | (1) |
|
D FPSO contracts - English law |
|
|
7 | (2) |
|
|
7 | (1) |
|
|
8 | (1) |
|
E FPSOs - contract structures |
|
|
9 | (6) |
|
|
9 | (1) |
|
|
10 | (1) |
|
|
11 | (1) |
|
(iv) Compliance with local content requirements |
|
|
11 | (1) |
|
(v) Alternative structures |
|
|
11 | (1) |
|
|
12 | (2) |
|
|
14 | (1) |
|
F Typical FPSO charter obligations |
|
|
15 | (3) |
|
|
15 | (1) |
|
(ii) Design and construction |
|
|
15 | (1) |
|
(iii) Installation and acceptance |
|
|
16 | (1) |
|
|
16 | (1) |
|
|
17 | (1) |
|
(vi) Liabilities and indemnities |
|
|
17 | (1) |
|
(vii) Offtake and offloading |
|
|
18 | (1) |
|
G Floating production in the future |
|
|
18 | (2) |
|
(i) Making carbon fuel production greener |
|
|
18 | (1) |
|
(ii) Using existing infrastructure to capture carbon |
|
|
19 | (1) |
|
(iii) New floating energy sources |
|
|
19 | (1) |
|
|
20 | (26) |
|
|
|
20 | (1) |
|
|
21 | (1) |
|
C The design development process |
|
|
22 | (5) |
|
(a) Illustration 1- off-spec hydrocarbons |
|
|
24 | (1) |
|
(b) Illustration 2- weather loading windows |
|
|
25 | (1) |
|
(c) Illustration 3- design assumptions |
|
|
26 | (1) |
|
D Changes to basis of design |
|
|
27 | (5) |
|
(i) Changes - some issues and illustrations |
|
|
27 | (1) |
|
(a) Illustration 4-insufficient buoyancy |
|
|
28 | (1) |
|
(b) Illustration 5-relaxation of design requirements |
|
|
28 | (1) |
|
|
29 | (1) |
|
(iii) Charter notice requirements |
|
|
30 | (2) |
|
|
32 | (3) |
|
(i) Allocation of design risk |
|
|
32 | (1) |
|
(ii) Separate hull and topsides yards |
|
|
33 | (1) |
|
(a) Illustration 6- interface design |
|
|
34 | (1) |
|
(b) Illustration 7- handover design |
|
|
34 | (1) |
|
|
35 | (1) |
|
G Compliance with local regulations |
|
|
36 | (2) |
|
|
36 | (1) |
|
|
37 | (1) |
|
(a) Illustration 8- flaring |
|
|
38 | (1) |
|
H Design changes of necessity |
|
|
38 | (5) |
|
|
38 | (1) |
|
(I) Preferential design changes |
|
|
39 | (3) |
|
|
42 | (1) |
|
|
43 | (1) |
|
(a) Illustration 9- scope of agreed variation |
|
|
43 | (1) |
|
L Post-delivery variations |
|
|
44 | (2) |
|
Chapter 3 Construction Contracts |
|
|
46 | (8) |
|
|
|
46 | (1) |
|
|
47 | (1) |
|
C Legal nature of a subcontract |
|
|
48 | (1) |
|
D Typical construction contract terms |
|
|
49 | (5) |
|
(i) Description/scope of work |
|
|
50 | (1) |
|
(ii) Price and payment terms |
|
|
50 | (1) |
|
|
51 | (1) |
|
(iv) Mechanical completion/commissioning |
|
|
51 | (1) |
|
|
51 | (1) |
|
|
52 | (1) |
|
(vii) Rights of termination |
|
|
52 | (1) |
|
(viii) Defects rectification |
|
|
52 | (2) |
|
Chapter 4 Conversions, Refurbishment And Modifications |
|
|
54 | (28) |
|
|
|
54 | (1) |
|
B Conversions versus newbuild projects |
|
|
55 | (1) |
|
|
55 | (2) |
|
(i) The vessel for conversion |
|
|
55 | (2) |
|
(ii) Incorporating the vessel into the design |
|
|
57 | (1) |
|
D The yard, scope of work and delivery |
|
|
57 | (4) |
|
|
57 | (1) |
|
(ii) Scope of work and fitness for purpose |
|
|
58 | (1) |
|
(a) Robin Rigg case study |
|
|
58 | (2) |
|
(iii) Delivery of the vessel to the yard |
|
|
60 | (1) |
|
|
61 | (8) |
|
|
62 | (1) |
|
|
62 | (1) |
|
|
63 | (1) |
|
|
64 | (1) |
|
|
64 | (2) |
|
|
66 | (1) |
|
|
67 | (1) |
|
(ii) Additional consequences of a variation |
|
|
67 | (1) |
|
|
68 | (1) |
|
(iv) Other types of variations |
|
|
68 | (1) |
|
|
69 | (3) |
|
(i) Delay: an illustration |
|
|
69 | (2) |
|
|
71 | (1) |
|
|
72 | (1) |
|
I Termination rights and carry over agreements |
|
|
73 | (3) |
|
|
76 | (1) |
|
J Redelivery and sailaway |
|
|
76 | (3) |
|
(i) Detention and/or arrest of the vessel |
|
|
77 | (1) |
|
(ii) Payment of final sums on redelivery |
|
|
77 | (1) |
|
(iii) Transfer of title and waiver of liens |
|
|
78 | (1) |
|
(iv) Impact of detention and/or arrest of the vessel |
|
|
78 | (1) |
|
|
79 | (2) |
|
|
81 | (1) |
|
Chapter 5 The Charter Period |
|
|
82 | (14) |
|
|
|
82 | (7) |
|
(i) The concept of delivery |
|
|
82 | (1) |
|
|
83 | (1) |
|
|
84 | (1) |
|
|
85 | (1) |
|
|
86 | (2) |
|
(vi) Commencement of acceptance tests |
|
|
88 | (1) |
|
|
89 | (4) |
|
(i) Acceptance test procedures |
|
|
89 | (2) |
|
(ii) Provisional acceptance/interim production |
|
|
91 | (1) |
|
(iii) Reservoir characteristics |
|
|
92 | (1) |
|
|
93 | (1) |
|
|
94 | (2) |
|
Chapter 6 Contractor Remuneration |
|
|
96 | (21) |
|
|
|
|
96 | (2) |
|
B Deductions from monthly payments |
|
|
98 | (2) |
|
|
100 | (2) |
|
|
102 | (2) |
|
|
104 | (4) |
|
(a) Illustration 1- time bars and draft invoices |
|
|
106 | (1) |
|
(b) Illustration 2 - time bars, completion of work, payment information given but not invoiced |
|
|
106 | (1) |
|
(c) Illustration 3- time bars and course of dealing |
|
|
107 | (1) |
|
F Enforcement of claims for non-payment |
|
|
108 | (1) |
|
|
108 | (1) |
|
H Limitation of liability for downtime |
|
|
109 | (1) |
|
I Performance adjustments to hire |
|
|
110 | (7) |
|
(i) Altera Voyageur - the facts |
|
|
110 | (3) |
|
|
113 | (1) |
|
|
114 | (1) |
|
(iv) Altera Voyageur - the judgment |
|
|
115 | (2) |
|
Chapter 7 Fpso Offloading |
|
|
117 | (15) |
|
|
|
117 | (1) |
|
B Offloading - the essentials |
|
|
118 | (5) |
|
(i) Offloading capability |
|
|
118 | (1) |
|
(ii) Offloading performance |
|
|
118 | (2) |
|
|
120 | (3) |
|
|
123 | (1) |
|
C Offloading operations and responsibility |
|
|
123 | (9) |
|
|
126 | (1) |
|
(D) Offtake vessel scheduling |
|
|
127 | (1) |
|
(i) Scheduling by the FP Contractor |
|
|
127 | (1) |
|
|
127 | (1) |
|
(ii) Scheduling by the Company |
|
|
127 | (1) |
|
(iii) Dedicated offtake vessels |
|
|
128 | (1) |
|
|
129 | (1) |
|
|
129 | (1) |
|
(vi) Voyage charters/COAs |
|
|
130 | (1) |
|
|
130 | (1) |
|
|
131 | (1) |
|
Chapter 8 Indemnity And Limitation Of Liability Clauses |
|
|
132 | (14) |
|
|
|
132 | (1) |
|
B Risk of personal injury/loss of life |
|
|
133 | (1) |
|
|
133 | (1) |
|
D Third-party property damage and personal injury/loss of life |
|
|
134 | (2) |
|
|
136 | (2) |
|
|
138 | (3) |
|
G Liability for wreck removal |
|
|
141 | (1) |
|
H Gross negligence and wilful misconduct qualifications to indemnity clauses |
|
|
141 | (1) |
|
I Overall cap on FP Contractor's liability |
|
|
142 | (1) |
|
|
143 | (1) |
|
K Split charter and O&M contracts |
|
|
143 | (1) |
|
|
144 | (1) |
|
M Interpretation of indemnity clauses |
|
|
145 | (1) |
|
|
146 | (12) |
|
|
|
146 | (1) |
|
B Introduction to the different types of policy relevant for any one field |
|
|
146 | (6) |
|
(i) Operators' extra expense/energy exploration and development/control of well insurance |
|
|
146 | (1) |
|
(ii) Construction all risks insurance |
|
|
147 | (1) |
|
(iii) Delay in start-up insurance |
|
|
148 | (1) |
|
(iv) Business interruption/loss of production income |
|
|
148 | (1) |
|
(v) Contingent business interruption |
|
|
149 | (1) |
|
(vi) Hull and machinery insurance |
|
|
149 | (1) |
|
(vii) War risks insurance |
|
|
149 | (1) |
|
|
149 | (1) |
|
(ix) Loss of hire insurance |
|
|
150 | (1) |
|
(x) Protection and indemnity insurance, including specialist operations cover |
|
|
150 | (1) |
|
(xi) Freight, demurrage and defence insurance |
|
|
151 | (1) |
|
|
152 | (1) |
|
C Insuring the FPSO during its operating life - property |
|
|
152 | (4) |
|
D Upgrades, life extension works and/or modifications |
|
|
156 | (1) |
|
|
156 | (2) |
|
Chapter 10 Intellectual Property Rights |
|
|
158 | (13) |
|
|
|
|
158 | (4) |
|
|
160 | (1) |
|
|
160 | (1) |
|
|
160 | (1) |
|
|
160 | (1) |
|
(v) Confidential information/trade secrets/know-how |
|
|
161 | (1) |
|
|
162 | (2) |
|
|
162 | (1) |
|
|
162 | (2) |
|
|
164 | (5) |
|
(i) Why licensing is important |
|
|
164 | (1) |
|
(ii) What is being licensed? |
|
|
165 | (1) |
|
(iii) Who is the licensee? |
|
|
166 | (1) |
|
(iv) What is the purpose of the licence? |
|
|
166 | (1) |
|
(v) Are royalties payable? |
|
|
167 | (1) |
|
(vi) Where can the licensee use the IP? |
|
|
167 | (1) |
|
(vii) How long does the licence last? |
|
|
168 | (1) |
|
|
168 | (1) |
|
(ix) Alternative to licensing - contractual exclusivity |
|
|
168 | (1) |
|
D Infringement risk: the limitations of warranties and indemnities |
|
|
169 | (2) |
|
|
171 | (14) |
|
|
|
171 | (1) |
|
B Express rights of termination |
|
|
171 | (2) |
|
(i) Termination for force majeure events |
|
|
172 | (1) |
|
(ii) Termination rights for the Contractor's default or the Company's default |
|
|
172 | (1) |
|
(iii) Termination for convenience |
|
|
172 | (1) |
|
(iv) Termination for delay |
|
|
173 | (1) |
|
|
173 | (1) |
|
D The rise of good faith obligations and relational contracts - is there a fetter on exercising a right of termination? |
|
|
174 | (5) |
|
(i) The Braganza implied term |
|
|
174 | (3) |
|
(ii) Relational contracts |
|
|
177 | (2) |
|
|
179 | (1) |
|
E Terminating in practice: two illustrations |
|
|
179 | (2) |
|
(i) Late arrival/acceptance at the oilfield |
|
|
179 | (1) |
|
(ii) Production difficulties |
|
|
180 | (1) |
|
F Effect of termination on other contractual terms |
|
|
181 | (1) |
|
G Other consequences of termination |
|
|
182 | (1) |
|
(i) The construction phase |
|
|
182 | (1) |
|
(ii) The production phase |
|
|
183 | (1) |
|
|
183 | (2) |
|
Chapter 12 Decommissioning |
|
|
185 | (15) |
|
|
|
185 | (1) |
|
B FPSO decommissioning projects and contracts |
|
|
185 | (5) |
|
(i) The disconnection and removal of the FPSO from the field and recycling of the FPSO |
|
|
186 | (2) |
|
(a) Illustration 1 -- North Sea Producer FPSO |
|
|
188 | (1) |
|
(ii) Well plugging and abandonment |
|
|
188 | (1) |
|
(iii) Removal, dismantling and disposal of subsea facilities including Christmas trees, pipelines etc. |
|
|
188 | (2) |
|
C Increased reputational risks |
|
|
190 | (1) |
|
D International obligations relevant to the decommissioning of offshore installations |
|
|
191 | (4) |
|
(i) United Nations Convention on the Law of the Sea (UNCLOS) |
|
|
191 | (2) |
|
|
193 | (1) |
|
|
193 | (1) |
|
(iv) Hong Kong International Convention for the Safe and Environmentally Sound Recycling of Ships (the Hong Kong Convention) |
|
|
194 | (1) |
|
(v) Convention on the Prevention of Marine Pollution by Dumping of Wastes and Other Matter 1972 (the `London Convention') and the London Protocol 1996 |
|
|
194 | (1) |
|
E EU Regulations relevant to the decommissioning of offshore installations |
|
|
195 | (2) |
|
(i) Waste Shipment Regulations 1013/2006 |
|
|
195 | (1) |
|
(a) Illustration 2 - the Eide Carrier |
|
|
196 | (1) |
|
(b) Illustration 3 - the HMS Laurence |
|
|
196 | (1) |
|
(ii) Waste Framework Directive 2008 |
|
|
196 | (1) |
|
(iii) Ship Recycling Regulation 1257/2013 |
|
|
197 | (1) |
|
F UK domestic legislation and regulatory regime applicable to decommissioning of offshore installations |
|
|
197 | (3) |
|
Chapter 13 Dispute Resolution |
|
|
200 | (11) |
|
|
|
|
200 | (1) |
|
B Dispute resolution procedures |
|
|
200 | (11) |
|
|
200 | (2) |
|
|
202 | (1) |
|
|
203 | (1) |
|
(iv) Tiered, or `escalation' resolution options |
|
|
204 | (1) |
|
(v) Contractual negotiations: `without prejudice' communications |
|
|
205 | (1) |
|
|
206 | (1) |
|
1 Base of commencement ot proceedings |
|
|
207 | (1) |
|
|
207 | (1) |
|
|
207 | (1) |
|
|
208 | (1) |
|
(vii) Litigation - English court proceedings |
|
|
209 | (2) |
|
Appendix A Floating production units - history, design, installation and operation |
|
|
211 | (46) |
|
|
|
211 | (4) |
|
|
211 | (1) |
|
B Early platforms for offshore oil production |
|
|
211 | (1) |
|
C The drive to deeper water |
|
|
212 | (1) |
|
D FPSO use on marginal fields - milder environments |
|
|
212 | (1) |
|
E FPSO application to harsh environments - North Sea |
|
|
213 | (2) |
|
F Technological barriers and breakthroughs for acceptance of FPSOs |
|
|
215 | (1) |
|
Part (ii) Different types of mobile production units |
|
|
215 | (13) |
|
|
215 | (1) |
|
B Characteristics of different hull types |
|
|
216 | (1) |
|
(i) Jackups and bottom fixed platforms |
|
|
216 | (2) |
|
|
218 | (2) |
|
|
220 | (1) |
|
(iv) Tension leg platforms (TLPs) |
|
|
220 | (2) |
|
(v) Floating production, storage and offloading vessels (FPSOs) |
|
|
222 | (1) |
|
(vi) FPSO buoy shaped (Sevan type) |
|
|
222 | (2) |
|
(C) Liquefied gas platforms |
|
|
224 | (1) |
|
(i) LNG regasification units (FSRUs) |
|
|
224 | (1) |
|
(ii) Floating LPG offtake |
|
|
225 | (1) |
|
(iii) Floating LPG production |
|
|
226 | (1) |
|
(iv) Floating LNG production vessels |
|
|
226 | (2) |
|
Part (iii) Comparison and selection of floating production options |
|
|
228 | (5) |
|
A Evaluation of alternative platform types |
|
|
228 | (2) |
|
B Impact of the reservoir on surface facility selection |
|
|
230 | (1) |
|
(i) Marginal field development |
|
|
230 | (1) |
|
(ii) Proportion of gas in the oilfield |
|
|
230 | (1) |
|
(iii) Difficult to handle crude oil |
|
|
231 | (1) |
|
C Oil export considerations in field development |
|
|
231 | (1) |
|
D FPSOs - advantages and disadvantages |
|
|
232 | (1) |
|
(i) Advantage - weight carrying efficiency |
|
|
232 | (1) |
|
|
232 | (1) |
|
(iii) FPSOs leverage shipbuilding technology |
|
|
232 | (1) |
|
(iv) Other primary advantages |
|
|
232 | (1) |
|
(v) Principal disadvantages |
|
|
232 | (1) |
|
(vi) Conclusions - when to use an FPSO |
|
|
233 | (1) |
|
Part (iv) Technical definition and design phases |
|
|
233 | (5) |
|
|
233 | (1) |
|
B Concept select, pre-FEED studies and basis of design |
|
|
233 | (1) |
|
|
234 | (1) |
|
D Functional specifications |
|
|
234 | (1) |
|
E FEED (front end engineering design) |
|
|
235 | (1) |
|
|
236 | (1) |
|
|
236 | (1) |
|
H Design interface and integration issues |
|
|
236 | (1) |
|
|
237 | (1) |
|
J Conflicting project philosophies |
|
|
237 | (1) |
|
Part (v) Topsides - some technical and operational issues |
|
|
238 | (5) |
|
|
238 | (2) |
|
B Separation and separators |
|
|
240 | (1) |
|
|
240 | (1) |
|
D Gas compression and gas treatment |
|
|
240 | (1) |
|
|
241 | (1) |
|
F Power generation and other utilities |
|
|
241 | (1) |
|
|
241 | (1) |
|
H Offshore performance testing |
|
|
242 | (1) |
|
I Operational efficiency, availability and uptime |
|
|
243 | (1) |
|
Part (vi) Mooring systems |
|
|
243 | (6) |
|
A Functions of the mooring system |
|
|
243 | (1) |
|
B Spread mooring or weathervaning? |
|
|
244 | (1) |
|
C Disconnectable mooring systems |
|
|
245 | (1) |
|
D Types of weathervaning system |
|
|
245 | (1) |
|
E Internal or external turret |
|
|
245 | (1) |
|
F Other options and typical choices |
|
|
245 | (2) |
|
|
247 | (1) |
|
H Turret design considerations |
|
|
247 | (1) |
|
I Bearings for weathervaning mooring systems |
|
|
248 | (1) |
|
|
248 | (1) |
|
Part (vii) Offtake operations |
|
|
249 | (8) |
|
A Oil offloading - introduction |
|
|
249 | (1) |
|
(i) Offloading - key considerations |
|
|
249 | (1) |
|
(ii) Offloading by tandem mooring from weathervaning FPSO |
|
|
250 | (2) |
|
(iii) Side-by-side offloading from weathervaning FPSO |
|
|
252 | (1) |
|
(iv) Offloading from spread moored FPSO |
|
|
252 | (1) |
|
(v) Offtake via remote loading buoy |
|
|
253 | (1) |
|
(vi) Offloading from DP FPSO to DP tanker |
|
|
253 | (1) |
|
|
253 | (1) |
|
(i) Cargo piping and pumping systems |
|
|
253 | (1) |
|
(ii) Tandem mooring equipment |
|
|
253 | (1) |
|
(iii) Floating export hoses for standard trading tankers |
|
|
253 | (1) |
|
(iv) Export hoses for dedicated shuttle tankers |
|
|
254 | (1) |
|
(v) Storage/deployment systems for non-floating hoses |
|
|
254 | (1) |
|
(vi) Floating hose storage |
|
|
254 | (1) |
|
(vii) Side-by-side offloading oil transfer equipment |
|
|
254 | (1) |
|
|
255 | (1) |
|
|
255 | (1) |
|
(ii) Operational requirements |
|
|
256 | (1) |
|
Appendix B FPSO case study |
|
|
257 | (2) |
|
Appendix C Legal glossary |
|
|
259 | (16) |
Index |
|
275 | |